Water Supply Scheme
Currently Running

AMRUT 2.0 — Kalaburagi Zone

Timeline
2024
Duration
Ongoing — DBOT (5 Years O&M + 1 Year DLP)
Location
Kalaburagi Zone, Karnataka
Client
Karnataka Urban Water Supply & Sewerage Board

Project Overview

Providing a large-scale Water Supply Scheme to Hatti, Kavithal, Manvi, Maski and Turvihal towns in Kalaburagi Zone under the AMRUT 2.0 programme. Executed through Design, Build, Operation and Transfer (DBOT) mode — encompassing complete hydraulic engineering design, construction of all water infrastructure components, and a comprehensive 5-year operational management commitment.

Scope of Work

Water supply scheme design and build for Hatti, Kavithal, Manvi, Maski & Turvihal
Source development, intake works and water treatment facilities
Rising main and distribution network laying across the Kalaburagi Zone
Town-level service reservoirs and household connection works
5-year O&M contract including 1-year DLP with performance guarantees

The Challenge

Integrating five towns with varying population densities, existing pipe networks in differing states of disrepair, and diverse topographic elevations into a single cohesive, balanced water distribution master plan.

Our Solution

Conducted extensive hydraulic modelling and demand forecasting for each town individually before developing a unified zonal water balance plan. Standardized on a single pipe procurement specification and adopted pre-fabricated pump house designs to accelerate construction timelines across all five towns simultaneously.

Project Impact

Ensuring reliable, metered, and safe potable water access for over 200,000 residents across five historically water-stressed towns in the Kalaburagi Zone, directly contributing to India's AMRUT 2.0 universal urban water coverage targets.